Construction Update for October 2020
Maxcon completed the full structure and façade to Level 23 during October 2020.
While fitout progress includes:
- Level 23 Window installation commenced
- Level 23 Balustrade & A/C boxes installed
- Level 22 Plaster complete
- Level 20 Joinery installed
- Level 21 Services (rough-in) complete
- Level 18 Services 2nd fix complete
- Level 17 Splash backs installed
- Level 17 Tiling complete
- Level 17 Stone installed
- Level 16 FFE installed
- Level 14 Bins Chutes installed
Maxcon are still on track for completion Q2 2021 with move-in from early Q2 2021.