Construction Update for November 2020
Maxcon are on track for completion Q2 2021 with settlements & move-in from early Q2 2021. In November they completed the installation of the Hot Water Unit & Solar Panels to Level 24 – Roof.
While fitout progress includes:
- Level 23 Plaster complete (just needs to be painted with Dulux Wash & Wear Low Sheen Paint in Lexicon Half for the walls)
- Level 23 Services (rough in) complete
- Level 22 Joinery installed that's the kitchen cupboards, vanity joinery & wardrobes to bedroom(s)
- Level 21 Tiling complete (floor & wall)
- Level 20 Services 2nd fix complete
- Level 19 Caesarstone Stone Benchtops installed
- Level 18 Bin chutes installed (Recycling & General waste rubbish chutes)
- Level 18 Lustre Glass splashbacks installed
- Level 18 FFE installed (that's the Bosch S/S Oven, Bosch S/S Gas Cooktop, Fisher & Paykel S/S Dishwasher, Artusi Range Hood, Caroma Vanity Basin, Abey Group - Gareth Ashton Tapware in Gunmetal)
- Level 5 Landscaping now 50% complete
- Ground Floor Windows installed
- Schindler Lifts 75% complete (you have 2 Qty in Penny Place)
- Fire Tank Installed
- Gas Meters Installed