Maxcon continued works during March with the construction works status as follows:
- Level 3, 4 & 5 slabs were poured
- Ground Floor block work completed
- Services for Ground Floor are 80% completed
- Level 1 fire sprinkler works commenced
- Precast core to Level 5 installed
- Formwork to Level 6 commenced
The key milestone achieved during March was the topping out of the podium, works can now proceed on the tower structure.