Construction Update for June 2020

Maxcon continued works during June completing Level 10 to Level 13 slabs with Level 7, 8 & 9 formwork stripped. Level 12 insitu columns poured including the sheer walls up to Level 12. Services works to Level 1 – 4 completed with sewer stacks, fire sprinklers and permanent lights. The carpark screen has been installed on the Western & North East boundary on Level 1 to 4 and sub-frames installed with sub-frame to the Southern elevation completed.

In addition, both precast panel cores have been installed up to Level 12 with internal core stairs poured to Level 7.

Fitout progress includes:

  • Concrete slabs Level 6 – 10 poured
  • Precast cores to Level 10 installed
  • Eastern side of carpark screens installed Level 1 - 4
  • Façade commenced with Level 5 windows installed
  • Internal plaster walls commenced