Maxcon continued works during July completing Level 14 to Level 17 slabs with Level 14 formwork stripped. Level 17 insitu columns poured.
Services works to Level 1 – 4 completed with sewer stacks, fire sprinklers and permanent lights. The carpark screen installed on all elevations except for Alimak area.
In addition, both precast panel cores installed up to Level 17 with internal core stairs poured to Level 12
Fitout progress