Construction works undertaken by Maxcon during January 2021 included:
- Commission and completion of internal building lift
- Penny Place entry signage installed
- Carpark line marking and concrete sealing complete
While fitout progress included:
- Level 20 - 23 Builders Defects & Clean
- Final detail paint touch ups to Level 6 – 12
- Final detail defect close out Level 6 – 12
- Level 23 bin chutes installed
- Corridor carpet installed Level 12 – 23
Completion is expected early-mid April 2021.