Construction Update for January 2020

Maxcon continued works during January completing the ground floor piling, footings, slab, and underground (hydraulics and fire) services. Ground to Level 01 insitu columns and walls were poured and stripped. In addition, ground floor precast panels were installed, and Level 01 slab formed.

The site compound extended capturing a portion of Nelson Street in accordance with SA Police requirements.