Construction Update for December 2020

With completion Q2 2021 and settlements & move-in from April 2021, Penny Place works continue to track ahead of schedule.

Progress includes:

  • Level 24 Solar panel installation complete
  • Level 23 Services roughed in
  • Level 23 Tiling complete
  • Level 22 Joinery installed
  • Level 21 Stone bench tops installed
  • Landscape civil works complete
  • Ground Floor window installation
  • Ground Floor amenities tiling